77 Coleman Street

Major redevelopment of a 1980s building adjacent to Underground tunnels. 78% of the existing structure was retained, and previously inaccessible green spaces has been unlocked for the public.

Location City of London
Client Kajima Partnerships
Architect Buckley Gray Yeoman
Status Complete (2020)
GIA 10,500m²
Feature

Key features

Extension with steel-framed structure

The existing sixth floor was replaced by a 3-storey steel-framed extension, providing two new levels of workspace.

Reconfiguring the cores

Re-coring with a braced steel frame, rather than the original reinforced concrete proposal, helped improve the construction programme.

Modified floorplates

Extensive internal demolition and new construction to modify the floorplates, creating generous floor-to-ceiling heights and making a feature of the retained structure.

New public thoroughfare

By extending the pre-existing Nun Court, new ground floor retail and leisure spaces are facilitated.

Awards

2022 OAS Development Awards City of London Refurbishment of the Year Won
2022 NLA Awards Shortlisted
2021 Building Awards Refurbishment of the Year Shortlisted
2021 AJ Retrofit Awards Shortlisted
Photography by Dirk Lindner